  1. A can do a piece of work in 20 days and B can do it in 30 days. How long will they take to do the work together?

    1. A10 days
    2. B12 days
    3. C11 days
    4. D20 days
    Show answer

    B 12 days

    Official TNPSC answer

    A's work rate is 1/20, B's is 1/30. Together, they complete 1/12 of the work per day, so they take 12 days.

  2. If 14 compositors can compose 70 pages of a book in 5 hours, how many compositors will compose 100 pages of this book in 10 hours?

    1. A12
    2. B10
    3. C8
    4. D7
    Show answer

    B 10

    Official TNPSC answer

    Each compositor sets 1 page per hour, so 100 pages in 10 hours needs 10 compositors.